Project awarded by the Mahatma Gandhi Institute following a call for tenders. The work covered the exterior repainting of the auditorium and the administrative and school buildings over a total surface area of approximately 6,600 m². The schedule was specially adapted to take into account the functions and events organized in the auditorium, with work carried out exclusively at night and on weekends.
- Anti-fungal exterior paint on an area of approximately 6,600 m²
- Auditorium (footprint of 1,960 m²)
- Administrative building and classrooms (3 floors, footprint of 2,545 m²)
- A schedule adapted to the functions and events in the auditorium
- Project cost: 2.9 million MUR (including VAT)
- Duration: 3 months (September to December 2022)