Painting work on the auditorium and the MGI school in Moka

Project awarded by the Mahatma Gandhi Institute following a call for tenders. The work covered the exterior repainting of the auditorium and the administrative and school buildings over a total surface area of ​​approximately 6,600 m². The schedule was specially adapted to take into account the functions and events organized in the auditorium, with work carried out exclusively at night and on weekends.

  • Anti-fungal exterior paint on an area of ​​approximately 6,600 m²
  • Auditorium (footprint of 1,960 m²)
  • Administrative building and classrooms (3 floors, footprint of 2,545 m²)
  • A schedule adapted to the functions and events in the auditorium
  • Project cost: 2.9 million MUR (including VAT)