This project was awarded by the Mahatma Gandhi Institute following a call for tenders. The work involved a complete exterior repaint of the building using antifungal paint, while preserving the original colors. All work was carried out at night to avoid any disruption to school activities, with daily cleaning of the site before classes resumed.
- Anti-fungal exterior paint on an area of approximately 3,850 m²
- Administrative block (3 floors, footprint of 747 m²)
- Classroom block (3 floors, 410 m² footprint)
- Sanitary block (2 floors, 80 m² footprint, with painted railings)
- perimeter wall, 120 m long
- Project cost: 0.7M MUR (including VAT)
- Duration: 1 month (June to July 2020)